St. Louis Construction News and Real Estate (CNR)

News | 11/10/2011

Helmkamp Near Completion on $45M Civil Job

Helmkamp Construction Co. is nearing completion on its portion of a Dry Flue Gas Desulfurization project to improve the quality of emissions at Dynegy's 1,800 MW coal-fired Baldwin Energy Complex in Baldwin, Illinois. Once the new systems come online, Dynegy Baldwin's sulfur dioxide emissions are expected to be the lowest of any coal-fired units in the state.

Helmkamp is completing $45 million in civil work including site preparation and installation of foundations for baghouses and dry scrubber equipment, the specialized equipment that removes sulfur dioxide from the coal plant's exhaust flue gases. In addition, Helmkamp installed foundations for duct supports, support buildings, utility racks and silo foundations. Helmkamp also is performing all excavations for the required mechanical and electrical underground installations.

"Helmkamp's performance on a project of this magnitude speaks volumes to their dedication, integrity and professionalism," said Dynegy Baldwin Vice President Kenneth Pollmann. Helmkamp has had a presence on the Dynegy Baldwin site for 13 years.

The 36-month project was complex and challenging, demanding precise coordination and communications to work within the fully operational power plant on a tight site between the Dynegy Baldwin plant and Baldwin Lake.

Helmkamp placed more than 4,000 anchor bolts and 2,500 auger cast piles at 60-foot depths with no reworks. They achieved that accuracy using a Robotic Total Station and desktop software to perform layout tasks, which allowed the team to easily re-establish pile locations as needed later in the project.

"Performing layout with conventional equipment would be too error prone for a project this complex," said Rob Johnes, Helmkamp vice president. "We use the Robotic Total Station for rough excavation, foundations, locating piers and reference points for anchor bolts and underground piping, and for offset work."

The project required approximately 30,000 cubic yards of concrete, much of it poured during two cold, snowy and icy winters. The largest single concrete pour was for the lime storage and waste ash silo foundation, in which three concrete pump trucks simultaneously poured a total 2,200 cubic yards of concrete in a limited access area. The second largest pour was approximately 1,300 cubic yards.